Shavano Park Street Reconstruction

Construction Updates:

Windmill

Clean Up and Vegetation Establishment is underway. Punch List and Closeout is underway.

Bent Oak

Clean Up and Vegetation Establishment is underway. Punch List and Closeout is underway.

Cliffside

Concrete Curb and Driveway installation is underway on Phase 1. Cement Stabilization on Phase 2 was completed on Wednesday and Concrete work is to follow shortly. Street Excavation will occur this week on Phase 3 early next week.

Construction Schedule

Wagon Trail - July 2023 to October 2023

End Gate - July 2023 to October 2023

Fawn 300 Block - September 2023 to February 2024

Chimney Rock - October 2023 to February 2024

Shavano Dr - November 2023 to March 2024

Fawn Dr - December 2023 to March 2024

Windmill Rd - February 2024 to April 2024

Bent Oak - March 2024 to April 2024

Cliffside Drive - March 2024 to August 2024

Saddle Tree Dr - August 2024 to November 2024


Road will be closed to through traffic during construction.

Please refrain form parking vehicles in the roadway during regular business hours (7am to 5pm) Monday - Friday.

We will make every effort to accommodate local residents access to their driveways and maintain all-weather surface during street construction.

For Immediate Assistance, Please Contact:

Site Superintendent - Barry Bonn (210) 371 - 6504

Project Manager - Gerald McLeod (830) 358 - 9206

Construction Updates:

Windmill

Clean Up and Vegetation Establishment is underway. Punch List and Closeout is underway.

Bent Oak

Clean Up and Vegetation Establishment is underway. Punch List and Closeout is underway.

Cliffside

Concrete Curb and Driveway installation is underway on Phase 1. Cement Stabilization on Phase 2 was completed on Wednesday and Concrete work is to follow shortly. Street Excavation will occur this week on Phase 3 early next week.

Construction Updates and Notifications

Project’s Construction Process:

Once a street is milled, SUBGRADE will need to be established and prepped for Cement Stabilization. After inspection of the Subgrade, CEMENT STABILIZATION (if needed) can occur. Trucks carrying bulk cement will be distributed across the Subgrade to be mixed into the material via a hydraulic mixing machine. Now mixed and graded to engineered elevation, SOIL TESTING must be conducted for quality control. With the material properly mixed, graded, and tested, the CEMENT TREATED SUBGRADE must cure for 24 - 72 hours.

After curing is completed, trenching for the Concrete Ribbon Curb will take place. Crews will then begin pouring the Concrete Curbs and Concrete Driveways. Concrete requires 3 - 7 days to properly cure and cannot be driven over.

Once concrete work is completed, Asphalt Paving may begin.

Project’s Construction Process

Once a street is milled, SUBGRADE will need to be established and prepped for Cement Stabilization.

After inspection of the Subgrade, CEMENT STABILIZATION (if needed) can occur. Trucks carrying bulk cement will be distributed across the Subgrade to be mixed into the material via a hydraulic mixing machine. Now mixed and graded to engineered elevation, SOIL TESTING must be conducted for quality control. With the material properly mixed, graded, and tested, the CEMENT TREATED SUBGRADE must cure for 24 - 72 hours.

After curing is completed, trenching for the Concrete Ribbon Curb will take place. Crews will then begin pouring the Concrete Curbs and Concrete Driveways. Concrete requires 3 - 7 days to properly cure and cannot be driven over.

Once concrete work is completed, Asphalt Paving will begin.